Successful First Blasting at Huzhou South Taihu Modern Bio-Industrial Park Site Preparation Project
Release Date:2012-03-27 00:00:00
Views:113

Successful First Blasting at Huzhou South Taihu Modern Bio-Industrial Park Site Preparation Project

The project is located near the Ning-Hang High-Speed Railway subgrade, bridges, and tunnel entrance, with complex surrounding conditions. After safety evaluation, it was classified as a Class A deep-hole blasting project.

The blasting area was divided into four sections with a total excavation volume of approximately 700,000 m³ and a construction period of 120 days. To ensure safety, our company optimized the blasting design and adopted different control measures for special, key, and conventional blasting zones.

The first blasting used hole-by-hole initiation technology, effectively controlling vibration and flyrock within the designed limits. Surrounding facilities remained intact, and the project received recognition from the owner and relevant authorities.